Reso 0209-11/1963 RESOLUTION NO. 209
RESOLUTION OF THE BOARD OF DIRECTORS OF THE SAN MARCOS
COUNTY WATER DISTRICT ESTABLISHING POLICY FOR PROPOSED
SUBDIVISION PROCEDURE REGARDING WATER AND/OR SEWER
SYSTEM AND PARPICULAR AGREEMENT FOR CONSTRUCTION OF
SAME WITH SUBDIVIDER.
BE IT RESOLVED by the Board of Directors of the San Marcos County Water
District as follows:
WHEREAS, the Board of Directors of the San Marcos County Water District
has determined that proper chronological prodedure be established for proposed
subdivision development regarding water and/or sewer system, and
WHEREAS, the Board of Directors of the San Marcos County Water District
has determined the necessity fer proper construction agreement for development of
water and/or sewer system within proposed subdivision development.
NOW, THEREFORE BE IT RESOLVED that policy shall be as follows:
1. Upon receipt of one print of Tentative Map, District
will write letter to Real-Estate Commissioner and
County Health Department stating the conditions of
service.
2. Upon submittal of three prints of the Tentative Map,
together with a deposit to cover the estimated cost of
engineering for hydraulic analysis and schematic system
layout, the District will determine the sizes and
locations of sewers, mains, valves, and hydrants required.
One print of the Tentative Map showing these facilities
schematically will be returned to the Developer or his
Engineer by the District's Engineer. The system shown
is subject to approval by the Directors.
3. District's Engineer will submit a print of the Tentative
Map showing system layout to the Directors with reco-
mmendation for approval. Notification of approval or
disapproval will be mailed to Developer or his Engineer.
4. Developer's Engineer prepares construction plans and
submits one set of prints to District's Engineer for
checking and approval.
5. Following approval of the construction plans, the
Developer shall enter into an Agreement with the District
providing for the construction of the systems to the
District standards, and also providing for the acceptance
of the completed systems by the District. Developer
shall not commence construction until the Agreement has
been approved and executed by the District. If a
RESOLUTION NO. 209 Page 2
commitment is required of the District as to water or
sewerage service, or if any portion of the District's
existing system is to be modified, a bond is required.
PASSED, ADOPTED AND APPROVED this 18th day of November 1963, by the
following polled vote:
AYES: Directors: Blanchard, Mahr, Paul, Smith and
Truesell
NOES: Directors: None
ABSENT: Directors None
Oby Blanchard, President of the Board
of Directors and the San Marcos
County Water District
Jeanne M. Gist, Secretary of the San
Marcos County Water District and Board
of Directors thereof
RESOLUTION NO. 209
RESOLUTION OF THE BOARD OF DIRECTORS OF THE SAN MAR COS
COUNTY WATE~ DISTRICT ESTABLISHING POLICY FOR PROPOSED
SUBDIVISION PROCEDURE REGARDING WATER AND/OR SEWER
SYSTEM AND PARTICULAR AGREEMENT FOR CONSTRUCTION OF
SAME WITH SUBDIVIDER
BE IT RESOLVED by the Board of Directors of the San Marcos County Water District
as follows:
WHEREAS, the Board of Directors of the San Marcos County Water District has
determined that proper chronological procedure be established for proposed subdivi-
sion development regarding water and/or sewer system, and
WHEREAS, the Board of Directors of the San Marcos County Water District has
determined the necessity for proper construction agreement for development of water
and/or sewer system within proposed subdivision development.
NOW, THEREFORE BE IT RESOLVED that policy shall be as follows:
1. Upon receipt of one print of Tentative Map, District will
write letter to Real-Estate Commissioner and County Health
Department stating the conditions of service.
2. Upon submittal of three prints of the Tentative Mahr, together
with a deposit to cover the estimated cost of engineering for
hydraulic analysis and schematic system layout, the District
will determine the sizes and locations of sewers, mains, valves,
and hydrants required. One print of the Tentative Map showing
these facilities schematically will be returned to the Developer
or his Engineer by the District's Engineer. The system shown is
subject to approval by the Directors.
3. District's Engineer will submit a print of the Tentative Map
showing system layout to the Directors with recommendation for
approval. Notification of approval or disapproval will be
mailed to Developer or his Engineer.
4- Developer's Engineer prepares construction plans and submits one
set of prints to District's Engineer for checking and approval.
5. Following approval of the construction plans, the Developer shall
enter into an Agreement with the District providing for the con-
struction of the system to the District standards, and also pro-
viding for the acceptance of the completed systems by the District.
Developer shall not commence construction until the Agreement has
been approved and executed by the District. If a commitmenthis
required of the District as to water or sewerage service, or if any
portion of the District's existing system is to be modified, a
bond is required.
PASSED, ADOPTED AND APPROVED this 18th day of November 1963, by the following
polled vote:
AYES: Directors: Blarechard, Mahr Paul Smith and Trussell
NOES: Directors: None
ABSENT: Directors: None
Oby Blanchard, President of the Board of
Directors and the San Marcos County Water Dist.
Jeanne M. Gist, Secretary of the San Marcos
County Water District and Board of Directors
thereof
SAN MARCOS COUNTY WATER DISTRICT
,,Suggested Chronological Procedure for Construction
of Water and Sewerage Systems inSubdivision-Type Delopments
1. Upon receipt of one print of Tentative Map, District will write
letter to Real-Estate Commissioner and County Health Depart-
ment stating the conditions of service.
2. Upon submittal of three prints of the Tentative Map, together
with a deposit to cover the estimated cost of engineering for
hydraulic analysis and schematic system layout, the District
will determine the sizes and locations of sewers, mains, valves,
and hydrants required. One print of the Tentative Map showing
these facilities schematically will be returned to the Developer
_ or his Engineer by the District's Engineer. The system shown is
subject to approval by the Directors.
3. District's Engineer will submit a print of the Tentative Map
showing system layout to the Directors with recommendation for
approval. Notification of approval or disapproval will be mailed
to Developer or his Engineer.
4. Developer's Engineer prepares construction plans and submits one
set of prints to District's Engineer for checking and approval. ~
5. Following approval of the construction plans, the Developer shall
enter into an Agreement with the District providing for the con-
struction of the systems to the District standards, and also pro-
viding for the acceptance of the completed systems by the District.
Developer shall not commence construction until the Agreement has
been approved and executed by the District. If a commitment is
required of the District as to water or sewerage service, or' iflany
portion of the District's existing system is to be modified, a
bond is required.
7 -8-64