Reso 1222-06/2004RESOLUTION NO. 1222
RESOLUTION OF THE BOARD OF DIRECTORS OF THE
VALLECITOS WATER DISTRICT APPROVING AMENDMENT OF THE
REVISED BASIC AGREEMENT TO ADDRESS PHASE V COST ALLOCATION
WHEREAS, the Encina Wastewater Authority ("EWA") is proceeding with design and
construction of an expansion of the Encina Water Pollution Control Facility in order to
increase the capacity of the Joint System, known as Phase V; and,
WHEREAS, section 17 of the "Revised Basic Agreement for Ownership, Operation
and Maintenance of a Joint Sewage System" ("RBA") provides for allocation of capital
expenses among the member agencies; and,
WHEREAS, section 11.1.2 of the RBA provides that it is the responsibility of the
Joint Advisory Committee to review and make recommendations regarding the proposed
expansion of the Joint System to the governing bodies of the member agencies; and,
WHEREAS, the RBA makes no provision for the allocation of the capital costs of
Phase V facilities;
WHEREAS, it is in the best interests of the member agencies that a cost allocation
for Phase V facility construction costs be included in the RBA; and
WHEREAS, the Board of Directors of Encina Wastewater Authority unanimously
adopted EWA's Resolution No. 2004-16 amending the RBA to include the provision for said
cost allocation;
NOW, THEREFORE, BE IT RESOLVED:
1. The Vallecitos Water District approves the following amendments to the RBA:
a. Section 17.3 is hereby added to the RBA to read:
17.3 Phase V Expansion. Phase V contract expenses approved by the
Operator/Administrator shall be paid once a month based on invoices from
the contractor or contractors, engineers, construction manager and any other
consultants. Unless otherwise specified, capital expenses shall be paid on
a quarterly basis by the member agencies. The Operator/Administrator shall
notify the member agency financial representatives of the amounts needed,
and whether supplemental capital billings will be required. Upon completion
and acceptance of all work authorized by the Operator/Administrator as part
of the Phase V Expansion, a final adjustment shall be calculated and paid in
accordance with Exhibit D.
Exhibit D is hereby added to the RBA to read as provided in "Exhibit
D," attached hereto.
Resolution No. 1222
Page 2
These amendments shall be effective as of the first date that all
member agencies have granted approval.
A certified copy of this resolution shall be forwarded to EWA immediately
upon its approval.
PASSED, APPROVED AND ADOPTED by the Board of Directors of the Vallecitos
Water District at a regular meeting held on the 16th day of June, 2004 by the following roll
call vote:
AYES:
NOES:
ABSTAIN:
ABSENT:
ATTEST:
CRUZ, DAVY, HANNAN, FERGUSON
Margar E. Ferguson, esi en
Board ~f~DEirectors
Vallecitos Water District
William W. Rucker, Secretary
Board of Directors
Vallecitos Water District
Resolution No. 1222
Page 3
Encina Wastewater Authority
Revised Basic Agreement
Exhibit D
Allocation of Phase V Capital Improvements
The cost of Phase V Capital Improvements shall be allocated by unit process and among flow, Bio-chemical
Oxygen Demand (BOD) and Total Suspended Solids (TSS) in the manner recommended for revenue
programs by the State Water Resources Control Board as amended by action of the Encina Wastewater
Authority (EWA) member agencies, Joint Advisory Committee and Board of Directors and as follows:
1. The replacement value of the existing Unit I and Unit J facilities at the mid-point of construction shall be
determined and, in addition, each member agency's share thereof shall be determined.
a. Replacement value shall be calculated for all Unit I and Unit J facilities remaining in service at Phase
V project acceptance including: Pre-Phase III; Phase III; Phase IV including interim flow equalization
facilities transitioning from Unit J to Unit I; and, Post Phase IV including the Building Program and
Joint Use Flow Equalization.
b. The replacement value of each facility shall be calculated by multiplying the original cost of that facility
by the percentage change in the Engineering News Record Construction Cost Index for Los Angeles
(ENRLA) from the year that facility was placed in service then adding the resulting product to the
original cost of the subject facility.
c. Mid-Point of Construction shall be the date half-way between the date EWA issues a Notice to
Proceed on the largest single Phase V Project construction contract and the date the EWA Board of
Directors takes action to accept that contract as completed.
d. Each member agency's current ownership percentage (COP) of the replacement values for existing
facilities shall be calculated by multiplying total Unit I Flow, Unit I Solids and Unit J Disposal
replacement values by each member agency's Unit I Liquid, Unit I Solids or Unit J Disposal
percentage capacity rights as stated in Section 9.1 of the RBA.
2. Based upon wastewater flow projections developed and refined by the member agencies, required
ownership percentages (ROP) shall be determined and, in addition, each member agency's share of
existing facilities at replacement value determined in Step 1 shall be restated to conform to their
respective ROP.
a. Flow projections shall be provided by the member agencies and shall not be changed to alter the
allocation of Phase V costs hereunder after the member agencies have unanimously approved this
amendment to the Revised Basic Agreement (RBA).
b. ROP shall be calculated by dividing a member agency's wastewater flow projection by the total of all
member agencies wastewater flows.
c. Each member agency's share of the replacement values for existing facilities shall be calculated by
multiplying total Unit I Flow, Unit I Solids and Unit J Disposal replacement values by each member
agency's ROP of Unit I Liquid, Unit I Solids or Unit J Disposal.
3. An estimated debit or credit shall be calculated for each member agency to pay for, or receive payment
or credit for, investments in existing Unit I and Unit J facilities and thereby reallocate ownership of existing
facilities at replacement value among the member agencies in conformance with their respective ROP
as determined in Step 2.
a. Where any member agency's ROP for Unit I Liquid, Unit I Solids or Unit J Disposal is greater than its
COP for Unit I Liquid, Unit I Solids or Unit J Disposal, an estimated debit shall be calculated and
assessed to that member agency's account for that unit process.
Resolution No. 1222
Page 4
b. Where any member agency's ROP for Unit I Liquid, Unit I Solids or Unit J Disposal is less than its
COP Unit I Liquid, Unit I Solids or Unit J Disposal, an estimated credit shall be calculated and credited
to that member agency's account for that unit process.
c. The debit or credit shall be calculated by subtracting each member agency's share of the replacement
values for existing facilities (determined in Step 1 d ) by unit process from that member agency's share
of the ROP (determined in Step 2c) by unit process.
d. Upon conclusion of this step for each unit process, each member agency's estimated share of all Pre-
Phase III, Phase III, Phase IV and Post-Phase IV Unit I and Unit J costs for facilities placed into, and
remaining in, service as of the most recent fiscal year end prior to Phase V project acceptance shall
be combined with the Phase V Project construction costs estimated in Step 4, to determine each
member agency's estimated Phase V Project cash requirements.
The total cost of the Phase V facilities at mid-point of construction shall be estimated by the design
engineer. As of July 1,2004 Phase V facilities construction costs are estimated at $36.1 million. These
costs shall be allocated to member agencies on the basis of each member agency's ROP.
Each member agency's share of the total cost of the Phase V Project shall be calculated by adding the
member agency's debit or credit as determined in Step 3 with the member agency's share of Phase V
costs as determined in Step 4. These amounts as of July 1,2004 are as follows (amounts in thousands
of dollars):
Estimated Estimated Total Estimated
Replacement Existing Phase V Cash
Value of Existing Facilities Debit or Estimated Phase Required by
Ownership (Credit) V Facilities Costs Member Agency
Vista $43,309 $7,270 $8,938 $16,209
Carlsbad $49,724 $(1,088) $ 8,595 $7,507
Buena $16,742 $(2,521 ) $2,513 $(8)
Vallecitos $40,565 $4,789 $8,590 $13,379
Leucadia $40,998 $(7,294) $5,956 $(1,338)
Encinitas $9,689 $(1,156) $1,508 $352
Total $201,026 $0 $36,100 $36,100
Final Phase V cost allocations shall be determined, and member agency accounts shall be adjusted in
accordance with Section 17.3 of the RBA, following completion of Phase V construction and shall use the
method described hereinabove except that actual figures shall be used including: existing facilities based
on the most recently completed independent financial audit; project costs based on actual amounts paid
according to EWA's financial records; and, actual ENRLA at the defined mid-point of construction.